ICI LONDON TIOXIDE PLANT

PROJECT PROFILE

CLIENT

ICI London

LOCATION

Burnie, TAS

INDUSTRY

Chemical

DURATION

1996 – 7 Months

SERVICE

Industrial Demolition & Deconstruction; and Asbestos & Hazardous Materials Removal

PROJECT OVERVIEW

Carried out on behalf of ICI London was the total demolition of the Tioxide Plant Burnie Tasmania.

16,000 tonnes of scrap steel was processed to export grade on site and loaded out form Burnie Port. Local skilled labour was sourced for the Project from the Burnie area and came together to complete the project in a total of 7 months, a staggering 5 months ahead of schedule without incident.

Picture 1 – 160 tonne Excavator

 

The bulk of the demolition was carried out by this 160 tonne excavator, equipped with the worlds’ largest rotating shear at the time.

Picture 2 – Demolition of an eighty story structure

In this picture, the 160 tonne excavator can be seen making the last cut to topple an eight story structure. The operator sits six metres off the ground and seventeen metres from the workface.

Picture 3 – Scrap Loading

Loading out of scrap to Burnie wharf by 70 tonne excavator equipped with a 170 HDR LaBounty grapple. Loading time for each semi trailer was reduced to under five minutes.

Picture 4 – Site Clean-up

Organization and good house keeping were the key to the successful completion of the Tioxide site, two months ahead of schedule. The entire site was processed using four hydraulic exca- vators in just 7 months.

DOWNLOAD PROJECT PROFILE

View the project profile to get more information on this project.