ENSHAM RESOURCES, DRAGLINE DLO3 DEMOLITION - COMET, QLD
PROJECT PROFILE
CLIENT
Idemitsu
LOCATION
Comet, QLD
INDUSTRY
Mining
DURATION
July 22 – Oct 22
SERVICE
Industrial Demolition
PROJECT OVERVIEW
Idemitsu engaged Major Projects Group (MPG) as the Principal Contractor to demolish the Bucyrus Erie 1260W Dragline (DL03).
The 1,680t dragline was located at the Ensham Resources mine site in Comet, QLD.
SCOPE OF WORK
Demolition and disposal of the Dragline 03 – Bucyrus Erie 1260W (1,680t).
UNIQUE CHALLENGES

Explosive cutting of the boom ropes.
Removal of the counterweight.
Demolition of the dragline housing.
Build-up of grease in the dragline’s rotating frame and undercarriage.
Heavy weight of individual dragline parts (e.g. hoist drum and drag drum).
METHODOLOGY
MPG Undertook a stability assessment of the dragline to determine the enabling works required prior to the explosive collapse of the boom and mast. The assessment showed that the MG Sets totalling 60t had to be removed to prevent any movement of the main structure once the boom had dropped.
For the controlled collapse of the dragline boom, the explosive team placed 8no charges on the mast support ropes. With the explosive cutting of the ropes, the mast and boom collapsed to the ground under its own weight. The boom and mast were then processed using MPG’s 33t excavator and steel shear progressively working through the structure processing into transportable sections.
The next step involved removing all the internal components and dragline housing using the 33t excavator. To enable the demolition of the housing, a demolition pad was created to ramp up to the rear of the housing. The excavator then progressively worked through the structure leaving the A-Frame structure.
The A-Frame structure was spilt into two sections and pre-weakened to allow the structure to collapse once the pull had been initiated. The remaining dragline structure was then dismantled using a combination of oxy-cutting, crane lifts, and induced collapses.
Finally, all steel was processed progressively using MPG’s excavator with shear attachment and oxy cutters.
RESULTS
In total, MPG undertook 12 induced collapse demolition drops and recorded a little over 3,300 man-hours. More than 1,300t of scrap steel was processed. There were 0 safety incidents during the whole duration of the works.
DOWNLOAD PROJECT PROFILE
View the project profile to get more information on this project.