Major Projects Group was selected by GrainCorp Ltd to demolish the no.2 ship loader at Carrington Wharf in New South Wales.

SCOPE OF WORK

The project included the demolition and removal of the approximately 258 tonnes rail mounted ship loader no. 2 at GrainCorp’s Carrington Wharf site, as well as the removal of a 48 tonne boom with loading spout and nozzle. The final step of the project was to recycle all scrap generated from the works.

UNIQUE CHALLENGES
 Working over water for the removal of the boom

 Potential for objects falling into the water

 Lead paint used on the entire structure

 Proximity to live wharf infrastructure

CUSTOMIZED SOLUTIONS

Major Projects Group removed the boom using a 250 tonne crane and dismantled the remaining structure using a 130 tonne crane and a 50 tonne crane. In order to process the demolished structural components, Major Projects Group used a 32 tonne excavator equipped with specialist demolition attachments.

RESULTS

The project was completed ahead of time, according to plan and within the allocated budget.

Project Testimonial

The project was managed very professionally. All workers on site appeared to be highly experienced. All equipment used was in excellent functional condition, and communication was good over entire project.

Colin N | Maintenance Supervisor

DOWNLOAD PROJECT PROFILE

View the project profile to get more information on this project.

Featured Projects

Battery Recycling Plant Demolition

Battery Recycling Plant Demolition

September 18, 2019
Dave Hukka
Koppers Pipeline and Gantry Demolition

Koppers Pipeline and Gantry Demolition

August 30, 2019
Dave Hukka
Linc 029 Dismantling of Pipework

Linc 029 Dismantling of Pipework

December 26, 2018
Dave Hukka
Queens Wharf Tower Demolition

Queens Wharf Tower Demolition

November 29, 2018
hnoguera
Ship Loader No 2

Ship Loader No 2

November 27, 2018
hnoguera
XSTRATA FSR Plant

XSTRATA FSR Plant

October 26, 2018
hnoguera
QAL Calciner Kiln

QAL Calciner Kiln

October 25, 2018
hnoguera
Pasminco Cockle Creek Smelter

Pasminco Cockle Creek Smelter

October 24, 2018
hnoguera